| |
True,
this sum was to cover the cost of the dam and power installation
(at Ajena), the opening up and equipping of the bauxite mines
and a complete plant for producing aluminum from bauxite to
be sited at Kpong. The scheme, in other words, was fully comprehensive
as it stood then. But it was also enormously costly with the
result that very extensive participation from outside sources
was essential. So it was that for the next few months, the
Government, in addition to an ambitious development program
in agriculture, education, health and so on, occupied itself
with seeking the necessary outside help. For instance, by
the time full Independence was achieved on 6th March 1957,
extensive meetings had already been held between the government,
the United Kingdom Government and two aluminum companies which
had originally declared themselves to be interested. Those
series of meetings, however, reached no firm conclusion. Indeed,
as time and the discussions went on, the chances of a successful
outcome seemed more and more remote. For one thing, this was
a period of financial stringency when interest rates on loans
and lengths of loan
repayments became less favorable. In addition, the world demand
for aluminum was temporally out-stripped by production capacity,
and finally,
over and above all this, the attitude of other Governments,
which might be interested in participation, was that Ghana
should first come to satisfactory arrangement with the aluminum
companies. The aluminum companies on the other hand, wanted
to be assured of certain factors in advance ? for example,
the cost of power. But the cost of power. In turn, depend
on the conditions on which other Governments might lend Ghana
money. If ever there were an example of a vicious circle,
this was one and to break it Dr. Nkrumah took the opportunity
to an official visit to the United States in July 1958 to
raise the problem with President Eisenhower. As a result of
their talk, a U.S. firm of consulting engineers, the Henry
J. Kaiser Company, was retained by the Ghana and U.S. Governments
to make a reassessment of the engineering aspect of the project
and the costs. Some seven months later, in March 1959, Kaiser
reported. They recommended that Akosombo gorge, originally
pinpointed by Kitson, provided and added that there was the
possibility of smaller hydro-electric projects at Kpong and
Bui which could follow as and when the need arose. They recommended
that the aluminum smelter should be built at Tema where the
new town and harbor were now rising fast, rather than at Kpong
as originally proposed and they urged that alumna should be
imported until revenue from the industry made it possible
to mine and refine the local bauxite into alumna. Finally,
though the smelter would be the all-important main user of
electricity from the power station, Kaiser suggested that
a 500-mile network of transmission lines should be installed,
covering the whole of southern Ghana. The new proposals represented,
of course, a drastic pruning back on the original concept,
especially in relations to the mining and refining into alumna
of the local bauxite. But it had important advantages to offset
this. For instance, the cost of the Akosombo Dam, generating
station, and township were now estimated to be ?102.5 million
(? 42.7 million), compared with an original estimate of 162.25
Million Cedis(?67.6 million) while the potential power out
has been raised from 564 MW to 768 MW, or about 22 times the
1959 power generating capacity of the country. Ghana, in short
stood to gain more power for less capital; outlay ? always
a satisfactory state of affairs. In addition certain other
technical changes had been made with the net result that the
total estimated cost had been reduced by more than 40 per
cent to 313.7 million cedis (?130.7 million).
Continue |
|